Member Entwistle opened and closed public forum, as there was none.
6. OLD BUSINESS:
None.
7. NEW BUSINESS:
A.
273 Enterprise Rd - Storage Facility - Pre-Application
Civil Engineer, Jeremy Anderson presented the conceptual plans for a 5 unit storage
facility.
Matthew West, Planning Manager, expressed concerns of school drop off area being
located directly across from the site.
Discussion occurred about traffic. Project Engineer, Eric Glissey, assured staff that the
applicant will work with Volusia County to formulate plans for traffic mitigation.
Mr. Glissey requested that staff allow a section along the southeast side of the
development to not be gated.
Deputy Utility Director, James Parrish discussed potable water and utility connections.
Assistant Fire Marshall, Samuel Schaller discussed hydrants and sprinkler systems.
Alternate Entwistle provided insight to the Final Site Plan submittal process.
B.
271 Fort Smith Boulevard - Change of Use for Restaurant -
Pre-Application
The applicant, Jasmarie Rosa presented the concept for a restaurant and bakery.
Brandon Hatch, Planner 1, discussed parking, landscaping and the need for a lot
combination with a neighboring parcel in order to increase parking spaces.
Deputy Utility Director, James Parrish, advised the applicant that a dumpster enclosure
would be required. He informed the applicant that the parcel is on septic and not
sanitary sewer.
The applicant expressed interest in using the second floor space to host events.
Assistant Fire Marshall, Sam Schaller discussed a change of use being needed for the
project.
C.
2100 Saxon Boulevard - Grocery Store - Final Site Plan
Project Engineer, Randi Holihan, presented plans to demolish an old grocery store and
replace it with a new and improved grocery store.
Discussion occurred about the original BPUD development agreement.