Works facility; that work was completed at a cost of $13,852 leaving
a balance of $236,148 for work at the primary building at the Public
Works Depot along with the sign shop.
The contract for the work on April 14, 2025 was awarded to A.G.
Pifer Construction Company, Inc. in the amount of $172,274. The
Scope of Work included roof gutter replacements, siding
repairs/replacement, masonry repair, exterior painting/water
proofing, flooring replacement, prime/paint interior, seal foundation
cracks, replace sinks/toilets/urinals/partitions, etc.
Change Order #1 was required to replace the window blinds that
have outlived their useful life and reinstallation would not be viable
as well as the need for replacement cabinets for three-bathroom
facilities for a total of $18,901 bringing the project cost to $191,175;
Change Order #1 was approved on June 9, 2025 by City staff.
During on-going construction it was determined that Change Order
#2 was necessary for additional cabinetry replacement that no longer
provided the physical support or needed space for office supplies,
radios, electronic equipment, manuals, handouts, etc., sign shop
subfloor replacement (not part of the initial contract), remove/replace
dysfunctional exhaust fans in bathrooms, remove/replace
deteriorated air supply grilles, and electrical outlet installations.
This is a request to approve Change Order #2 with A.G. Pifer
Construction Company, Inc. in the amount of $34,398.03, leaving
the project under budget with a remaining budget of $10,574.97.
City staff has deemed this additional work in Change Order #2 as
necessary.
B.
The City utilizes piggyback contracting as a resource in the
procurement method of goods and services. A piggyback method is
utilized by public agencies, schools, colleges, and other government
agencies and allows an agency to obtain equipment, materials,
supplies, and other services using a different agency’s existing
contractual agreement. In order to utilize an existing contract, the
goods, services, or commodities needed must be within that existing
contract. The ability to utilize a competitively bid existing contract
often provides another agency with the benefit of a lower price than
what can be obtained in a direct bid.
Background:
Fausnight Stipe & Line, Inc. out of Longwood, Florida was awarded a
competitively bid agreement from Seminole County for the work
proposed to be performed in Deltona under Contract
IFB-604562-23/LNE. The City of Deltona and Fausnight Stipe &
Line, Inc. entered into an Amendment Piggyback Agreement on
March 18, 2025, that is valid through August 28, 2026.