Legislation Details

File #: 2015-6317    Version: 1
Type: Resolution Status: Agenda Ready
File created: 10/8/2026 In control: City Commission
On agenda: 10/19/2026 Final action:
Title: Request approval of Resolution No. 2026-95 to award the competitively bid Lake Windsor Stormwater Force main Relocation to GPS Civil Construction, Inc. of Ormond Beach, Florida.
Attachments: 1. Resolution 2026-95 Award ITB 26027, 2. BID TAB-BID# 26027-Lk Windsor SW Force Main Relocation, 3. GPS Civil -Lake Windsor Bidinal bid package-GPS Civil, 4. CCI - Lk Windsor SW FM Reloc

TO:  Mayor and Commission                                          AGENDA DATE:  10/19/2026

 

FROM:  City Manager                                          AGENDA ITEM:    4 - A                                                               

                                                                    

SUBJECT:                        

Title

Request approval of Resolution No. 2026-95 to award the competitively bid Lake Windsor Stormwater Force main Relocation to GPS Civil Construction, Inc. of Ormond Beach, Florida.

Body

 

LOCATION:

Courtland Boulevard from Windsor Heights Street to Belkin Court

 

COST:

Not to Exceed $1,618,770

 

SOURCE OF FUNDS:

Stormwater and ARPA Funds

 

ORIGINATING DEPARTMENT:

Public Works

 

POTENTIAL MOTION:

Recommendation

I move to approve Resolution No. 2026-95.

END

 

BACKGROUND:

Background

Stormwater has the required funds as part of the adopted Fiscal Year 2026 - 2027 budget.  This project budget is a combination of Stormwater & Grant monies from the American Rescue Plan Act (ARPA). 

 

When the City of Deltona was incorporated, it inherited an existing stormwater force main located along the rear of properties within a 10-foot drainage and utility easement. At the time, impacts on homes were limited. However, the area is now nearly built out, making access to the ageing 8-inch force main extremely difficult. Staff has also faced challenges completing timely repairs when the force main is needed to support pumping operations during storms, hurricanes, and rainy seasons.

 

The relocation and upsizing of the force main provides the City ease of implementation of pumping activities; access for any requisite repairs and mitigates any liability to the City to private property should the existing force main fail.

 

 

The project bid specifications and plans (Bid #26027) were submitted on Demand Star, Thursday, September 10, 2026. There was a mandatory pre-bid held on Thursday, September 17, 2026, and bids were submitted and opened on Monday, October 12, 2026 @ 3pm. There were ten (10) qualified bids received. The qualified low bidder was GPS Civil Construction, Inc. with a bid of $1,059,391.00.  GPS has performed utility work in the past for The City of Deltona with positive results and no negative issues.

 

Due to the pending deadline to expend the required ARPA funds by December 31, 2026, if the City is unable to move forward with GPS Civil Construction, Inc. the City Manager will move to the second lowest bid with Carr & Collier, Inc.

 

The total cost, to include contingencies, shall not exceed $1,618,770 without seeking Commission approval.

End