File #: 15-8661    Version: 1
Type: Contract Status: Passed
File created: 3/26/2024 In control: City Commission
On agenda: 4/1/2024 Final action: 4/1/2024
Title: Request consideration and approval for the bid received from A.G. Pifer Construction Company, Inc. of Daytona Beach, Florida for the upland, Phase I Site Restoration Efforts associated with the 4B Project in an amount not to exceed $144,781.00 - Phyllis Wallace, Interim Public Works Director (386) 878-8965. Strategic Goal: Infrastructure
Attachments: 1. 4B Phase 1 Site Restoration Approval Memo, 2. 4B Phase 1 Site Restoration Bid Tabulation ITB24005, 3. 4B Phase 1 Site Restoration ITB 24005, 4. Recommendation of Award_Deltona Community Center Site Restoration

TO:  Mayor and Commission                                          AGENDA DATE:  4/1/2024

 

FROM:  Interim City Manager                                          AGENDA ITEM:    9 - D

                                                                    

SUBJECT:                        

Title

Request consideration and approval for the bid received from A.G. Pifer Construction Company, Inc. of Daytona Beach, Florida for the upland, Phase I Site Restoration Efforts associated with the 4B Project in an amount not to exceed $144,781.00 - Phyllis Wallace, Interim Public Works Director (386) 878-8965.

 

Strategic Goal:  Infrastructure

 

Body

LOCATION:

980 Lake Shore Drive

 

COST:

$144,781.00

 

SOURCE OF FUNDS:

4B Construction Project 401650-650100-41014

 

ORIGINATING DEPARTMENT:

Public Works/Deltona Water

 

STAFF RECOMMENDATION PRESENTED BY:

That the Commission approve and authorize the approval for the bid received from A.G. Pifer Construction Company, Inc. of Daytona Beach, Florida for the upland, Phase I Site Restoration Efforts associated with the 4B Project in an amount not to exceed $144,781.00 - Phyllis Wallace, Interim Public Works Director (386) 878-8965.

 

POTENTIAL MOTION:

Recommendation

“I move to approve the bid received from A.G. Pifer Construction Company, Inc. of Daytona Beach, Florida for the upland, Phase I Site Restoration Efforts associated with the 4B Project in an amount not to exceed $144,781.00  The City Manager has the authority to make corrections of scrivener’s errors and the like.”

END

 

BACKGROUND:

Background

The project known as the Alexander Avenue 4B Intake Project (4B Lakeshore) has been determined to be un-constructable.  As the City works with the other project partners including but not limited to the SJRWMD, FDEP and the West Volusia Water Supply Committee for full & complete project closeout, it was determined that the upland site (landscaping) restoration was the prudent step in the project closeout.

 

The landscaping plan is intended to restore as best as possible the natural state of vegetation prior to project cleaning & construction activities. The plant materials chosen closely replicate what was originally there, except in size. The project also includes removal of electrical panels/transformers, roadway repair/restoration as well as refurbishment of the shell boat parking lot. This restoration effort will compliment what was undertaken, inhouse, on the shoreline of Lake Monroe a few months ago.

 

The City solicited bids with notification being broadcast to 885 companies and there were 20 plan holders and 3 watchers with only 1 bid received. The City did not require a mandator pre-bid meeting & site inspection but received only 1 bid. That bid from AG Pifer Construction Company, Inc. is within industry standards and prior work efforts with this firm have been completed to the satisfaction of the City of Deltona.

End